Cunningham were appointed to deliver extensive enabling works and site diversions to facilitate a €400 million state-of-the-art manufacturing facility.
Extensive earthworks and foundations were carried out by our team. Complex site services were carried out including MV, ELV, Storm, Foul, Drainage, Fire Main, Process Drainage and Watermains.
Works were carried out, without disturbance, to an ongoing live manufacturing operation facility.
At a glance
Project Name
Bristol Myers Squibb
Sector
Mission Critical
Client
Bristol Myers Squibb
Value
€9,500,000
Duration
Ongoing
related case studies